Citi's AI capex math
Business · Heat 1.1 / 10 · 2 shows · 24m airtime
On November 3, 2026, Citi's Heath Terry said data center projects expected by December are slipping to the second or third quarter of next year, held up by permitting, power, labor and equipment. About 5 gigawatts of U.S. projects, roughly 20% of the 2028 pipeline, now shift into 2029. Morgan Stanley estimates a 44 gigawatt power shortfall through 2028, about 38% of projected demand, though it later revised the figure to the mid-30s after the midterms. Virginia outlawed on-site gas generation, Norway imposed a moratorium and a large UK project was terminated over grid access. The argument now splits on whether this is a pause or a relocation: Byrd expects a pause, not cancellation, while Joe Moore says Texas and…
How 2 podcasts covered it
- Bloomberg Surveillance, 2026-11-03 (23:53 to 34:26)
Breaks down the data center project delays
Citi's Heath Terry walks through the infrastructure bottleneck: projects slated for December are sliding to Q2 or Q3 next year on permitting, power, labor and equipment, which softens spot markets. He pairs that with hyperscaler numbers - backlog up 142% year over year, AI revenue growth accelerating 900 basis points - and a 26% cash return against 6% borrowing costs.
New angle: Data center projects expected by December are slipping to Q2 or Q3 next year on permitting, power, labor and equipment. - Thoughts on the Market, 2026-11-11 (1:40 to 2:38)
Puts numbers on Citi's capex slippage
Puts numbers on the slippage Citi's Terry flagged: about 5 gigawatts, roughly 20% of the 2028 pipeline, moves into 2029, with 2027 untouched and hyperscaler capex held at $1.6 to $1.8 trillion. Frames it as a delay that lengthens the cycle, not a cut.
New angle: About 5 gigawatts of U.S. data center projects, roughly 20% of the 2028 pipeline, shift into 2029. - Thoughts on the Market, 2026-11-11 (2:38 to 4:06)
Adds Morgan Stanley's 44 gigawatt power shortfall
Adds Morgan Stanley's power-side number to the delay story: a 44 gigawatt shortfall in U.S. data center power through 2028, about 38% of projected demand. Frames the bottleneck as shifting from equipment to power and walks through who absorbs it best.
New angle: Morgan Stanley estimates a 44 gigawatt U.S. data center power shortfall through 2028, roughly 38% of projected demand. - Thoughts on the Market, 2026-11-13 (0:11 to 2:41)
Reports Morgan Stanley's revised shortfall number
Opens the episode by putting Stephen Byrd on the record with a revised Morgan Stanley number: the shortfall moves from 30 gigawatts to the mid-30s after the midterms, with Texas and Ohio named as the gubernatorial delays behind it.
New angle: Morgan Stanley revised its 2028 power shortfall from 30 gigawatts to the mid-30s after the midterms. - Thoughts on the Market, 2026-11-13 (2:44 to 5:01)
Lists Virginia, Norway and UK grid setbacks
Byrd walks through the options for closing the shortfall and puts new specifics on the record: Virginia outlawed on-site gas generation, Norway has a moratorium, and a large UK project was terminated when the utility could not provide grid access in time. He also argues grid optimization is overhyped because utilities plan for worst-case days.
New angle: Virginia outlawed on-site gas generation for data centers, Norway imposed a moratorium, and a large UK project was terminated over grid access. - Thoughts on the Market, 2026-11-13 (5:04 to 6:46)
Frames the slowdown as a pause, not cancellation
Byrd, asked to play pundit after the midterms, frames the slowdown as a pause rather than cancellation: developers in Louisiana are bankrolling hospitals and teacher, police and fire pay raises to win community support. A qualitative read on the political path, not a new number.
New angle: Byrd expects a pause, not cancellation, with developers in Louisiana funding hospitals and teacher, police and fire pay raises. - Thoughts on the Market, 2026-11-13 (6:46 to 9:48)
Argues power shortages will not slow the buildout
Brings in Joe Moore to push back on the power-shortfall bear case: he says 2027 component shortages are getting worse, memory is the top hyperscaler complaint, and developers will relocate rather than slow down. Adds a market read - memory stocks down 60-70% at about three times earnings.
New angle: Joe Moore says power constraints in Texas and Ohio will not slow the buildout; developers will relocate. - Thoughts on the Market, 2026-11-13 (9:54 to 11:41)
Recaps the capex debate and IPO visibility
Joe Moore's answer on timing: the worst case is a quarter-by-quarter grind proving 2028 with 12-month lead times, and visibility into AI economics will come from companies going public. Stays inside the capex-and-power debate already on the record.